Hutton Lift Station Rehabilitation

  • January, 2015
  • City of Farmers Branch

Project Overview

Felix served as the General Contractor for the rehabilitation of a Sewer Lift Station for the City of Farmers Branch, TX.  Our scope included removal and replacement of four 6 in. submersible pumps, discharge piping and appurtenances.  Removal of the existing wet well coating and recoat concrete wet well.  Build a new masonry electrical room attached to the existing CMU building. Removal and replacement of the MCC and electrical equipment.  The lift station required maintaining 24 hour bypass for the duration of the project .

Services Rendered

Construction Services: Mechanical, Structural Concrete, Electrical, Equipment Installation.