Lift Station Emergency Generators

  • September, 2015
  • North Texas Municipal Water District

Project Overview

Felix was the General Contractor for this project that included civil improvements, electrical modifications, and installation of standby generators at five North Texas Municipal Water District lift stations.

Each site needed to be fully operational 24 hours a day. Working with the North Texas Operation’s staff, Felix was able to develop critical MOPO’s that allowed each facility to remain in operation without disruption. Each site had it’s own complexities during construction including public interference, multiple subcontractors on site, limited accessibility, and allowing plant operations staff full access to each site.

Services Rendered

Construction Services: Mechanical, Civil, Concrete Flatwork.