Sherman UV Disinfection System Replacement

  • March, 2016
  • City of Sherman

Project Overview

Felix was the General Contractor on this wastewater treatment plant UV disinfection system replacement project in Sherman, TX.

Our scope included removing and replacing two UV systems, one at a time, and four slide gates. The concrete channel had to be modified to fit the new UV system. One channel had to remain operational at all times in order to keep up with the plant flows. Our team self-performed 90% of the total project scope and was able to deliver a successful installation over 30 days ahead of schedule due to proper pre-planning and a accurate bid scope.

Services Rendered

Construction Services: Mechanical, Electrical.